Key Points
- The State Corporation Commission opened its evidentiary hearing Tuesday in Richmond on NextEra’s proposed $67 billion acquisition of Dominion Energy.
- Commission staff have recommended against approving the deal as proposed; the companies have accepted 101 of 117 proposed conditions.
- The hearing is expected to last several days, and a commission decision is due by Jan. 11, 2027.
RICHMOND, Va. — The Virginia State Corporation Commission opened its evidentiary hearing on Tuesday on NextEra Energy’s proposed $67 billion acquisition of Dominion Energy, according to the State Corporation Commission.
The hearing began at 10 a.m. at the commission’s building in Richmond and is expected to last several days. The public can attend in person or watch a video livestream, the commission said.
The case, No. PUR-2026-00112, asks the commission to approve the acquisition of control of Virginia Electric and Power Company, Dominion’s Virginia utility, as part of the planned merger between Dominion Energy Inc. and NextEra Energy Inc., according to the commission.
The all-stock deal would create the world’s largest regulated utility. In rebuttal testimony filed on Nov. 3, the two companies said they had accepted 101 of the 117 conditions proposed by commission staff and the Attorney General’s consumer counsel, and another 13 with enhancements or modifications, according to the companies’ filing with the U.S. Securities and Exchange Commission.
Commission staff took a harder line in October. In prefiled testimony, staff concluded the companies had not shown the deal meets the state Utility Transfers Act standard of protecting adequate service at just and reasonable rates, and recommended it not be approved as proposed. Gov. Abigail Spanberger filed testimony asking that the companies be required to freeze residential electricity rates for six years and triple customers’ bill credits if the merger proceeds.
Opposition has also come from lawmakers and school officials. Five Virginia House members urged the commission on Nov. 13 to reject the deal as written, and the Fairfax County School Board urged the commission to deny it in a Nov. 11 letter that said Dominion will soon raise the school division’s own electricity costs by 24.9 percent.
Courtroom space in Richmond is extremely limited because of the number of participants, and seats are first-come, first-served, the commission said. Anyone attending in person should expect to show identification, sign in and go through security screening.
The commission faces a Jan. 11, 2027, deadline to decide the case. The companies have said they expect the transaction to close in the second half of 2027 if the required approvals arrive.
Also Read: Five Virginia Lawmakers Ask SCC to Deny Dominion-NextEra Deal